Brick Size mm
|
Approx. weight per Brick (kg)
|
No. of bricks in a Truck (8tons
capacity)
|
No. of Bricks / cub mtre
|
600x200x200
|
20 (+ or – 1)
|
400
|
41
|
600x200x150
|
15 (+ or – 1)
|
600
|
55
|
600x200x100
|
10 (+ or – 1)
|
800
|
83
|
Manufacturers of Lightweight (Cellular Lightweight Concrete) Bricks
Contact 9440013202
Saturday, April 6, 2013
Sizes of our CLC Bricks
Tuesday, April 2, 2013
Process of Manufacture of CLC Bricks
Machines we are using :
1. Mixer (Ribbon Type)
2. Conveyor
3. Water Pump
4. Foam Generator
5. Digital weighing system
6. Compressor
7. Control Panel
8. Trollies to carry slurry
9. Water tank 2000 ltrs capacity
10. Foam Tank 500 ltres capacity
11. Platform Trollies
12. Molds
Materials :
1. Cement
2. Fly Ash
3. Protein Foam (Veg)
4. Water
5. Demoulding oil
Process :
To manufacture one m3 CLC Bricks, first we fill the water as per requirement with pump from water tank, Later we run the conveyor and conveyor belt drops 500 kgs of Fly ash into the Mixer. Flyash and Mixer will be started simultaneously. We drop the 5 bags i.e., 250 kgs of 53 grade OPC cement in to the Mixer. Later 1.2 kgs of foaming Agent diluted with 30 litres of water will be added and mixed thoroughly. Air bubbles thoroughly mixes in cement and flyash slurry. At this point the one litre slurry taken out from Mixer and weighed for density. If it shows the required density, the slurry will be drained into trollies and these trollies transports slurry to the place where molds kept. This CLC cement slurry poured into molds. The outer frame of the molds removed after 18 to 24 hours and the separation plates removed after 48 afters. Then the finished CLC Bricks removed to curing area and curing will be done for 28 days. From 29th day onwards our CLC Bricks ready for sale. We are using 600mm x 200mm x 100/150/200mm molds.
1. Mixer (Ribbon Type)
2. Conveyor
3. Water Pump
4. Foam Generator
5. Digital weighing system
6. Compressor
7. Control Panel
8. Trollies to carry slurry
9. Water tank 2000 ltrs capacity
10. Foam Tank 500 ltres capacity
11. Platform Trollies
12. Molds
Materials :
1. Cement
2. Fly Ash
3. Protein Foam (Veg)
4. Water
5. Demoulding oil
Process :
To manufacture one m3 CLC Bricks, first we fill the water as per requirement with pump from water tank, Later we run the conveyor and conveyor belt drops 500 kgs of Fly ash into the Mixer. Flyash and Mixer will be started simultaneously. We drop the 5 bags i.e., 250 kgs of 53 grade OPC cement in to the Mixer. Later 1.2 kgs of foaming Agent diluted with 30 litres of water will be added and mixed thoroughly. Air bubbles thoroughly mixes in cement and flyash slurry. At this point the one litre slurry taken out from Mixer and weighed for density. If it shows the required density, the slurry will be drained into trollies and these trollies transports slurry to the place where molds kept. This CLC cement slurry poured into molds. The outer frame of the molds removed after 18 to 24 hours and the separation plates removed after 48 afters. Then the finished CLC Bricks removed to curing area and curing will be done for 28 days. From 29th day onwards our CLC Bricks ready for sale. We are using 600mm x 200mm x 100/150/200mm molds.
Subscribe to:
Posts (Atom)